Quick answer
How is the coal made, and where in the process do the problems I know come from?
The factory buys coconut shell charcoal from Sulawesi and turns it into briquettes in eight stages, from cleaning and sorting to packing and loading. The coals are dried in the ovens for 2 to 3 days, to 3–4% moisture, and weathered before packing. Each stage of making shisha charcoal is shown with the problem it can cause and the check that catches it.
1. The eight stages, and the problem each can cause
The charcoal passes through eight stages at the plant. The first is a delivery: the factory does not make its own shell charcoal, which is why the source of that input is something it tells the buyer about before changing.
| Stage | What happens, as declared | The problem it can cause | The check |
|---|---|---|---|
| 1. Incoming shell charcoal | Bought ready-made, from Sulawesi | Ash, smell | Ash; burn test |
| 2. Cleaning and sorting | A magnet removes iron objects, before crushing | An iron object in a coal | The magnet; no other screening is declared |
| 3. Crushing | The shell charcoal is crushed | An uneven mix | Shows later, in the burn test before the oven |
| 4. Mixing | Mixed with a tapioca binder; the ratio is not declared | Smell, cracks | Burn test before the oven; drop test after packing |
| 5. Pressing and cutting | Pressed and cut to the shape ordered; the settings are not declared | Size, burn time and heat | Size, count, burn test |
| 6. Oven drying | 2 to 3 days in the ovens, to 3–4% moisture | Coals that go out, cracks | Moisture and burn test after the oven |
| 7. Weathering | The coals rest after the ovens and before packing | A container that fails the shipping condition | The weathering certificate |
| 8. Packing and loading | Packed in bags, boxes and cartons, and loaded | Count, breakage, damp | Moisture at packing; size, drop test, count and burn test after packing |
Definition
briquette
A briquette is a piece pressed from ground material and a binder into a fixed shape.
Each problem in the third column has a page: too much ash, a smell when lighting, cracks and crumbling, a burn that is too fast or too cool, coals that go out, a foreign object in a coal, pieces of uneven size and coals that took in damp.
2. Where the checks sit in the process
The six checks are not spread evenly through the process. They sit at three points, and the oven is the dividing line: it runs for 2 to 3 days, and there are 4 of them for a declared 5 tons a day.
| Point in the process | Checks done there | What they catch |
|---|---|---|
| Before the oven | Burn test | A fault found before the drying days are spent on the batch |
| After the oven | Moisture, burn test | Coals that are not dry, or that smell or smoke when lit |
| At or after packing | Moisture at packing; size, drop test, count and burn test after packing | Damp, wrong size, weak pieces, a wrong count |
The sixth check, ash, has no declared stage, so the table does not place it. The full grid, with what each check is for, is under the six checks at each stage, and what the factory commits to across all of them under how the coal stays the same in every container.
3. What is not done here: carbonizing
The factory does not carbonize coconut shell. It buys coconut shell charcoal ready-made, from Sulawesi, and its own work starts when that charcoal is cleaned and sorted.
| Step | Where it is done |
|---|---|
| Turning coconut shell into charcoal | Before the charcoal reaches the factory; not at this plant |
| Cleaning, sorting, crushing and mixing | At the factory |
| Pressing, cutting and oven drying | At the factory |
| Weathering, checking, packing and loading | At the factory |
This matters to a buyer for one reason: the shell charcoal decides much of the ash and some of the smell, and it is an input the factory buys. As declared: The factory tells the buyer before it changes the shell charcoal source, the binder, the press settings or the packaging.
Tip
Ask for that notice in writing with your order, and keep a reference carton from each container. A change of source shows first in the ash.
4. What the factory does not declare
Four details of the process are not declared by the factory, and this page gives no figure for them. They are listed so that a buyer knows what to ask.
| Detail | Status | Where the answer for your order is |
|---|---|---|
| The press settings | Not declared | In the count per kilogram on your specification sheet |
| The ratio of binder to charcoal | Not declared | Ask with your quote |
| The number of weathering days | Not declared as a figure of this plant | On the weathering certificate for your order |
| What is burned in the test before the oven | Not declared | Ask with your quote |
The paper that records the rest period of an order is described on the page about the weathering certificate. What surrounds the coal at the last stage is under how the charcoal is packed, and the plant's size is on the page about the factory.
To ask about a stage for your order, name it in the form below or on the quote request page. An answer from the factory is added to this page once it is declared.